Review and finish wizard

Figure 19. Example review changes commissioning wizard dialog for SoftJACE


Example review changes commissioning wizard dialog for SoftJACE

To review and finish the Commissioning Wizard

After the final selected step in the Commissioning Wizard, a “Review of changes” dialog appears, as shown in Figure 19. It lists a summary of all remaining actions to be performed by the wizard.

Before proceeding:

  1. Read through the summary of changes, using the scroll bar to see those steps near the end.

    • If no change is needed, click the Finish button to initiate the rest of the Commissioning Wizard.

    • If any change is needed, click the Back button until the step dialog appears, then make the change. Then, click the Next button until this review dialog appears again.

  2. While the wizard is working, progress updates are posted in a “Completing Commissioning” dialog. When the wizard completes, a “Close” button is available. If any TCP/IP changes were made, the wizard reboots the SoftJACE.



  3. Click the Close button to exit the wizard.

    If the SoftJACE reboots, your platform connection to it drops. Notice that in the Nav tree, the platform instance for it is now dimmed.

  4. If you changed the IP address of the SoftJACE, close that platform instance, as it is now invalid.

    NoteGoing forward, you must access the SoftJACE by its new IP address (if changed). Note that your Workbench keeps a history of TCP/IP changes made. Also, remember to login using any new assigned platform credentials, see Platform daemon authentication.

    NoteAllow at least 2 minutes for the SoftJACE to reboot, before reopening a platform connection to it.

After running the Commissioning Wizard, you may still need to do some NiagaraAX platform configuration for the SoftJACE. See Post-wizard SoftJACE configuration.